Overload Testing
We have developed a wide range of overload tests in full compliance with SOLAS regulations and MODU codes.
These require five-yearly load tests on all lifeboats, FRCs, release mechanisms and davits. Overload testing is also required during installation and commissioning of new and reconditioned equipment.
All overload tests are performed by ISO 9001-controlled procedures using calibrated equipment including water bags, load cells and flow meters. Load tests include:
- five-yearly 110% overload tests on lifeboats and davits as required by SOLAS and MODU codes
- five-yearly 110% on-load lifeboat release and retrieval systems tests (these can be performed by the use of water bags or hydraulic jacks)
- 220%, 150% and 110% overload tests during the installation and commissioning of new or reconditioned lifeboats, davits and winches.